The installation process is very simple and quick. However, care must be taken during handling and installation to avoid damaging tile surfaces and edges.

Step 1: Prepare the Substrate

Prepare a clean, dry and perfectly level concrete substrate before installation.
Do not install cement tiles directly onto a fresh concrete or an unlevelled compacted cement-sand base, as this may cause tiles to become uneven, loose, cracked or broken over time.
Allow approximately 20mm below the finished floor level: 
Step 2: Apply Adhesive or Mortar 

Tiles can be installed by using tile adhesive or thin-bed mortar. For good adhesion:
     
 
Step 3: Lay the Tiles

Carefully place the tiles to avoid chipping the edges.
After laying, adjust and level the tiles using straightedge and hand pressure. Do not use a rubber mallet as impact may cause cracks.
Maintain a very narrow joint of approximately 1mm between tiles.
    
       
 
Step 4: Clean Immediately 

Immediately remove any excess adhesive or mortar from the tile surfaces and edges using damp cloth or sponge.
Do not allow adhesive or mortar to dry on the tile surface, as it may become difficult to remove.
Protect the finished floor and allow the adhesive or mortar to cure completely before grouting.

 

Step 5: Grouting 

Fill the joints with suitable cementitious grout.
White grout is generally recommended for the most neutral appearance, white other colors may be selected according to the design.
Remove excess grout from the tile surface before it dries.
 
   

Step 6: Cleaning and Sealing

After grouting, clean the floor with mild soap and clean water and allow it to dry completely.
Apply suitable penetrating sealer from qualified manufacturer according to the manufacturer's instructions.
Always test the sealer on one tile or a small inconspicuous area before applying it to the entire floor.

  
   

Step 7: Periodic Resealing

Depending on traffic and usage, reseal the floor every 12-24 months or as recommended by the sealer manufacturer.

TIPS
OFFICES & FACTORIES:
Company VST BUILDING MATERIALS PRODUCTION JSC.,
Adddress 16TM3B-C3 The Manor Central Park, Hanoi, Vietnam
Tel/Fax +84 (24) 3 821 0142
Mobile +84 (0) 97 432 3333 (Int’ Roaming/Whatsapp/Viber/WeChat)
Email  info@VietnamSTONEandTILE.com
   
Factory 1   Kien Duc Ward, Đak R'Lap Dist., Đak Nong Prov., Viet Nam
Factory 2   Pham Thi Giay Str., Hoc Mon Dist., HCM City, Viet Nam
Factory 3  Yen Dinh Ward, Yen Lam Dist., Thanh Hoa Prov., Viet Nam
LOCATION